RAM Environmental are chosen to install a new welding fume extraction system.
We were approached by Tex Engineering to provide a welding fume extraction system to serve seven welding bays at their Ipswich factory.
Tex manufacture a multitude of products for the road laying industry as well as trailers, kiosks and gas burners. With such a diverse product range RAM Environmental had the task of designing and installing a system which met with their varied needs.
We specified a 11kw centrifugal fan protected with star delta control gear. Eight Oskar fume extraction arms were installed throughout the factory. The trailer manufacturing bay required a coverage of 7 meters to ensure welding fumes could be extracted at source effectively. To overcome this we installed a 3 meter extension boom along with a 4 meter fume extraction arm giving the required coverage. The remaining welding bays were furnished with a mixture of Oskars standing and hanging fume arms depending on the requirements.
Upon completion the system was commissioned and a report issued to provide TEX with all the necessary commissioning data.
Workers at TEX noticed a significant improvement in air quality in the factory and are pleased with quality and design of the system.
Gallery
Test caption Services 1 item 2
Test caption Services 1 item 1
Test caption Services 1 item 3
RAM impressed us straight away they had a very personal approach and worked hard to give us an effective solution that suited our workshop. We have since been impressed with the quality of the equipment and installation all done at the right price. Great job!
Platinum Sheet Metals - Scott Brooks, General Manager March 2017
We use cookies to offer an improved online experience. By clicking "ACCEPT" without changing your settings you are giving your consent to receive cookies. Read our Privacy Policy for more details.